Water, fire and power
Standby generators and fuel systems
A standby set spends its life not running, and has to start anyway. Ratings and sizing, what goes into a generator room or acoustic enclosure, exhaust silencers, bulk and day tanks with their fill points and pumps, and the testing that keeps it ready.
70%Average load limit over 24 hours for standby and prime ratings under ISO 8528-1
AS/NZS 3010Electrical installations – generating sets, including changeover and interlocking
40–80%A typical day tank level band kept by automatic transfer pumps
Ratings and sizing
| ISO 8528-1 rating | Typical duty | Hours | Load |
|---|---|---|---|
| Emergency standby power (ESP) | Back-up when the mains fails | Limited, typically up to about 200 hours a year | Average up to 70% of the rating |
| Prime power (PRP) | Main supply where there is no grid, or regular peak lopping | Unlimited | Variable, average up to 70%, short overload allowed |
| Limited-time power (LTP) | Planned outages and peak shaving | Up to about 500 hours a year | Up to 100% |
| Continuous power (COP) | Base load at constant output | Unlimited | Constant, no overload |
Size on the running load plus the biggest step: motors starting direct on line, lifts and UPS rectifiers draw much more than their running current. Check voltage and frequency dip against what the loads tolerate, and derate for altitude and high ambient temperature.
Changeover and essential loads
Electrical
- An automatic transfer switch (ATS) starts the set on mains failure and transfers the load when voltage and frequency are stable.
- Changeover devices must be interlocked so the generator can never back-feed the network (AS/NZS 3010).
- Separate essential and non-essential boards so only the loads that matter run on the set.
- Life-safety loads (fire pumps, smoke control, lifts for firefighting) have their own rules; in NZ emergency power is specified system SS14.
UPS alongside generators
- A UPS bridges the 10–15 seconds the set takes to start and carries the load through transfer.
- Rectifier harmonics need a generator with a suitable alternator and voltage regulator; oversize where the UPS is a big share of the load.
Generator room and acoustic enclosure
Air path
- Intake acoustic louvres and attenuators, a plenum, then the engine and radiator, then discharge attenuators and louvres.
- The radiator fan moves a lot of air; check the free area and pressure loss of every louvre and attenuator against the engine maker’s limit.
- Fire dampers in the room intake where it crosses a fire separation.
Enclosures and doors
- Steel panels with about 32 kg/m³ acoustic infill behind perforated sheet, galvanised and powder coated for outdoor life.
- Acoustic doors with compression seals, stainless hinges and bottom shoot bolts; label left- or right-hand on the drawings.
- Anti-vibration mounts under the set and under the enclosure stop vibration reaching the building.
- Check transport limits early: a 2.4 m wide load travels freely, wider loads only at limited times.
Exhaust
- Flexible bellows at the engine, then spools, a riser and a silencer, with a rain cap or flapper at the outlet.
- Silencers come in grades from industrial to critical; a typical body is 1.6–2 mm steel with perforated linings and long-strand wool.
- Lag hot sections, keep clear of combustibles, and fit permanent lifting lugs to cylindrical silencers.
- Check total back pressure against the engine limit.
Fuel system
Tanks
- Bulk tanks are single skin in a bund, or double skin with interstitial leak monitoring; built to AS 1692 and installed to AS 1940.
- Fire-rated tanks inside buildings use a sprayed fire-resistant layer between the skins.
- A day tank is used when the bulk tank is far from the engine (more than about 15 m), above it, or well below it.
- A base tank under the set gives a compact package for smaller sites.
Fittings and pipework
- Typical sockets: fill with a drop tube, supply with foot valve, return, dipstick, tank vent, bund vent and spares.
- A locked fill point cabinet with an overfill prevention valve, level gauge and high-level alarm.
- Above-ground fuel pipe in stainless steel with compression fittings; check valves, ball valves rated for diesel and water-separating filters.
Transfer and controls
- Duty and standby transfer pumps fill the day tank from the bulk tank.
- A 4–20 mA level sensor keeps the day tank between set levels, with high and low alarms to the BMS.
- The return line and an overflow or break tank handle excess fuel; the day tank must always supply more than the engine burns.
Testing and readiness
- FactoryPressure test each tank, check welds and coatings, and fit nameplates showing the standard, capacity and safe fill level, with a dip chart.
- DeliveryProvide lifting drawings and certified lifting points; check sling angles and crane access.
- CommissioningLoad bank test at site, prove the ATS, alarms and fuel controls, and record the results.
- MonthlyRun the set on load where possible; long running at light load causes wet stacking.
- YearlyLoad bank test, fuel quality check and polishing, service filters, batteries and coolant.