Codes and materials
How building services projects run
Most of a consultant’s work is not drawing. Design stages and deliverables, coordination in BIM, specifications, producer statements, construction monitoring, commissioning and the compliance schedule, from concept to handover in New Zealand and Australia.
PS1 / PS4Design and construction review producer statements in New Zealand
CANConsultant’s advice notice: how a consultant instructs changes through the contract
NZS 3910The usual head contract form in New Zealand
Design stages
- ConceptChoose systems, set plant space and riser sizes, and give the cost planner rates per square metre.
- Preliminary designLoads and airflows, plant schedules, single-line diagrams and main routes coordinated with the architect and structural engineer.
- Developed designSized layouts, schedules, seismic and fire strategies, and a draft specification.
- Detailed design and documentationCoordinated drawings and specification for consent and tender, with the PS1.
- ConstructionAnswer RFIs, review shop drawings and submittals, issue CANs, and observe the work to the agreed monitoring level.
- CompletionWitness commissioning, review O&M manuals and as-builts, issue the PS4, and set up the compliance schedule.
Coordination and documents
BIM and drawings
- Model services in Revit or similar, then run clash detection with structure and other trades.
- Precast walls usually cannot be cut after casting; agree penetrations early.
- Show ceiling space and access zones; flexible duct can squash only a little before it chokes the airflow.
Specifications
- Masterspec in New Zealand and NATSPEC in Australia give the clause framework.
- Name performance, approved products and "or equal" rules, testing and commissioning, and what goes in the O&M manual.
- Keep the interfaces clear: who supplies power, controls, penetrations and fire stopping.
Change control
- Instructions go through the contract: a CAN from the consultant, or an engineer’s or site instruction under the head contract.
- RFIs get a written answer and a log; verbal answers cause disputes later.
Producer statements and sign-off
New Zealand
- PS1 design, PS2 design review, PS3 construction, PS4 construction review; councils decide which they accept.
- Engineers who sign PS1 and PS4 are usually Chartered Professional Engineers (CPEng).
- Seismic restraint of services is often designed partly by the contractor, so agree who designs it and the monitoring needed for the PS4.
- Specified systems go on the compliance schedule; the owner then issues a building warrant of fitness every year.
Australia
- Registered building certifiers or surveyors approve the work; several states register engineers and designers.
- NSW requires regulated designs and compliance declarations for class 2 buildings under the Design and Building Practitioners Act 2020.
- Essential safety measures are maintained and reported each year under state rules.
Commissioning and handover
Commissioning
- Plan it early: a commissioning plan, pre-functional checks, then functional tests witnessed by the consultant.
- Air and water balancing to the design flows, with reports.
- Controls: point-to-point checks, then sequences and alarms, then trend logs over some weeks.
- Fire mode and essential power tested from the real triggers.
Handover
- O&M manuals, as-built drawings, warranties, certificates and training for the facilities team.
- Seasonal commissioning and a defects period visit to tune the controls.
- Compare measured energy with the design and act on the gaps.
Related guides and tools
Sources
Checked October 2026. Standards and rules change; confirm the current edition before you rely on them.